“Time is money” could become the motto of SOLAR STEELCONSTRUCTION, which, thanks to the well-coordinated work of designers, managerial staff and construction departments, implemented the 7.1 MW “Zlatopolskaya-2” project in record time – 40 days.
Key technical characteristics of the object:
Panel capacity – 7.1 MW
Panels’ type – Jinko JKM385M 385 W, total quantity – 18 480 pcs
Inverter type – Huawei Sun2000-100KTL-M1, total number – 59 pcs
Forecast annual generation of “green” electricity – 8 427 MW / h
Social significance for the region:
- 12 new job opportunities
- About 750 thousand UAH annual payment of taxes to the local budget and more than 4 millions per year to the central budget
“Our company has been preparing for the implementation of this project for about two months. Back in December 2019, a general contract was signed, and all the main equipment was purchased in March-April 2020. Before embarking on a project with such a record time, we carefully assessed the risks: financial and reputational, calculated our production capabilities and … accepted this challenge. The goals for 2021 are more ambitious. The main task is to become even stronger than we are, and more resistant to external challenges,” – says Eugeniy Kornilov, Deputy Development Director of SOLAR STEELCONSTRUCTION – “After all, today our company has entered the markets of the near abroad and must gain a reputation on “foreign” territory.”
At the moment, the entire complex of construction and installation works has been completed, adjusting works are being performed, as well as external connection of the station to the networks of PJSC Kirovogradoblenergo. The planned start of the station is September 1, 2020. In the future, the station provides for the installation of storage-systems for the accumulation of generated energy for the facility’s own balancing.